lane closure

South Vine Street Lane Closure

Date: 
March 26, 2013 - 7:00am to March 29, 2013 - 4:00pm

Duce Construction will be installing a sanitary manhole on Vine Street between Oregon Street and Nevada Street. The southbound lane of Vine Street will be closed to traffic beginning on Tuesday March 26th at 7:00 AM, weather permitting, and ending on Friday March 29th at 4:00 P.M. The northbound lane will be open at all times.

Southbound traffic on Vine Street will be detoured via Oregon Street to Broadway Avenue to Washington Street, and back to Vine Street.

Thank you in advance for your patience and cooperation during the southbound lane closure on Vine Street. We apologize for any inconvenience this may cause.

University Avenue Lane Closures

Date: 
March 20, 2013 - 7:00am to March 22, 2013 - 5:00pm

New traffic signals will be installed at the intersection of Race Street and University Avenue as part of the Boneyard Creek Improvements Project. The City’s Contractor, Champaign Signal and Lighting, will be closing the southern eastbound lane and northern westbound lane of University Avenue at its intersection with Race Street starting on Wednesday March 20, 2013 at 7:00 A.M. weather permitting for installation of temporary traffic signals. The lane closures on University Avenue are projected to take until Friday March 22, 2013 at 5:00 P.M. to complete.

Two way traffic on University Avenue will be maintained at all times. Only one lane will be affected at a time and these are only daytime closures.

 Thank you in advance for your patience and cooperation during the University Avenue lane closures. We apologize for any inconvenience this may cause.

Broadway Avenue Lane Closures

Date: 
June 23, 2013 - 5:00pm

Sidewalk and parkway improvements will be constructed on Broadway Avenue as part of the Boneyard Creek Improvements Project. The City’s Contractor, Feutz, will be closing the outside south bound lane on Broadway Avenue starting on Wednesday March 20, 2013 weather permitting to work on sidewalk and parkway improvements along the west side of Broadway Avenue.

After the improvements on the west side are completed the north bound outside lane will be closed to complete improvements on the east side. The lane closures on Broadway Avenue are projected to take until June 23, 2013 to complete.

Two way traffic on Broadway Avenue will be maintained at all times. Access will be maintained to all businesses on Broadway Avenue during the improvements. On-street parking will remain available on the opposite side of the street from the lane closure.

Broadway Avenue will continue to be the detour route for Race Street. Thank you in advance for your patience and cooperation during the Broadway Avenue lane closures.

Griggs Street Lane Closure West of Race Street

Date: 
February 18, 2013 - 8:00am to February 22, 2013 - 4:00pm

O’Neil Brothers will be doing sewer work as a part of the Boneyard Creek Improvements Project.  In order to perform bypass pumping while the sewer work is occurring, a portion of the west bound lane of Griggs Street between Race Street and Central Avenue will be closed.  The closure will occur in the vicinity of the bridge over the Boneyard Creek.  This work is scheduled to begin on Monday February 18, 2013 at 8 A.M. and extend through Friday February 22, 2013 at 4:00 P.M., weather permitting.

The east bound lane of Griggs Street will remain open at all times during the lane closure.

We apologize for any inconvenience this may cause.

 

Vine Street Lane Closure

Date: 
January 14, 2013 - 7:00am to January 18, 2013 - 4:00pm

Duce Construction will be installing a sanitary manhole in the center turn lane of South Vine Street between Oregon Street and Nevada Street weather permitting from 7 A.M. on Monday January 14, 2013 to 4 P.M. Friday January 18, 2013.  Northbound and southbound lanes will be open at all time and only the center turn will be impacted.

 

We apologize for any inconvenience this may cause

Washington Street Lane Closure

Date: 
December 19, 2012 - 7:00am to December 24, 2012 - 8:00am

Starting Wednesday December 19th at 7:00 AM weather permitting, Washington Avenue between Walnut Street and Broadway Avenue will be reduced to one travel lane for the installation of a sanitary manhole.  The work should be completed by Monday December 24th at 8:00 AM.

 

We apologize for any inconvenience that it may cause.

Updated University Avenue Lane Closures at Maple Street - August 8th

Date: 
August 8, 2012 - 7:00pm to August 9, 2012 - 6:00am

The Urbana Champaign Sanitary District’s contractor Insituform will be doing sewer lining as part of the District’s annual sanitary interceptor maintenance program.  In order to line the sanitary sewer interceptor pipe the inside east and west bound lanes of University Avenue at its intersection with Maple Street will have to be closed. The two lanes of University Avenue will be closed from 7:00 P.M. on Wednesday, August 8, 2012 to 6:00 A.M. on Thursday, August 9th weather permitting.


Two-way traffic on University Avenue will be maintained at all times during the lane closures.


We apologize for any inconvenience this may cause.


Concerns or questions may be directed to Ms. Christine Childress of Sodemann & Associates at (217) 352-7688.

University Avenue Lane Closures at Maple Street - August 6th

Date: 
August 6, 2012 -
8:00am to 3:00pm

The Urbana Champaign Sanitary District’s contractor Insituform will be doing sewer lining as part of the District’s annual sanitary interceptor maintenance program. In order to line the sanitary sewer interceptor pipe the inside east and west bound lanes of University Avenue at its intersection with Maple Street will have to be closed. This work is scheduled to start on Monday August 6th and last from 8:00 A.M. to 3:00 P.M.  weather permitting.


Two-way traffic on University Avenue will be maintained at all times during the lane closures.


We apologize for any inconvenience this may cause.


 


Concerns or questions may be directed to Ms. Christine Childress of Sodemann & Associates at (217) 352-7688.

California Avenue Lane Closure

Date: 
November 4, 2011 - 7:00am to November 7, 2011 - 5:00pm

The City is making sanitary sewer repairs on California Avenue between Cedar Street and McCullough Street. California will be reduced to one lane of traffic beginning at 7:00 A.M. on Friday November 4, 2011 to Monday November 7, 2011 at 5:00 P.M. weather permitting.


We apologize for any inconvenience this may cause.

Main Street Lane Closure

Date: 
October 10, 2011 -
6:00am to 4:00pm

Advanced Wayne Cain & Sons Roofing will be closing the south east bound lane of Main Street between Vine Street and Broadway Avenue on Monday October 10, 2011 from 6:00 A.M. to 4:00 P.M weather permitting. Through traffic on Main Street will be maintained at all times.


We apologize for any inconvenience this may cause.