UCSD Sewer Lining Project Lane Closures

Date: January 17, 2012 - 8:30am to January 20, 2012 - 5:00pm

As part of the Urbana Champaign Sanitary District’s Annual Sanitary Interceptor Maintenance Project, the District’s Contractor Insituform will perform lining of an 18-inch sanitary interceptor that runs north along Urbana Ave.


Insituform will line Urbana Ave from Illinois Street to Main Street starting on Tuesday, January 17, 2012 at 8:30 A.M. and ending on Thursday January 19th at 5:00 P.M. weather permitting.


Insituform will also be lining along Oregon Street from Vine Street to Urbana Ave. Work along Oregon Street will start Friday January 20 at 8:30 A.M. and be completed by 5:00 P.M. that day weather permitting. The work along Oregon Street will cause a small portion of Oregon Street to be closed. The section of Oregon Street that is to be closed is from the intersection of Walnut Street to Vine Street.


Traffic will be affected on the following streets during the lining work:



  • Oregon Street from Walnut Street to Urbana Avenue

  • Urbana Avenue from Illinois Street to Main Street

  • Main Street at its intersection with Urbana Avenue

One or more lanes of a street may be closed at these locations to accommodate the Contractor’s equipment and set-up. We apologize for any inconvenience this may cause.

Click on location marker to view address.
Contact Reference: 
Created on: Friday, January 13, 2012 - 13:59
- Author: BradB