Get Solar Energy
Solar Installation Checklist
Usually Performed By |
Item |
Owner/Installer |
Determine if your roof gets enough sun with Google App |
Owner |
Review consumer protection guidance |
Owner/Installer |
Review Zoning Rules on Page 66 of City Zoning Ordinance |
Owner |
Consider bids from “qualified person(s)” |
Installer |
Apply for building permit and electrical permit. Building Permit: $6 per $1,000 of the estimated costs for the project, minimum $50. Electrical Permit: $6 per $1,000 of the estimated costs for the project, minimum $50. (217) 384-2443 |
Owner/Installer |
Apply for Ameren Net Metering |
Owner/Installer |
Apply for Ameren Distributed Generation |
Installer |
Request Building Safety Inspection (217) 384-2443 |
Installer |
Submit an Ameren Certificate of Completion |
Installer |
Submit an Ameren Installer Certification |