Public Works Projects

Project Project Status Estimated Completion Estimated Cost Contact Reference
Dr. Ellis Resurfacing Project Not Started August, 2020 $330,000 Shannon Beranek, Justin Swinford
Kinch Street Intersection Lighting Project Not Started August, 2020 $190,000
Stormwater Master Plan Not Started Justin Swinford
2019 Concrete Sidewalk Repair Project In Progress September, 2019 $110,000 Adam Shaw
2018-2020 Miscellaneous Sewer Repair Project In Progress April, 2020 $600,000 Justin Swinford, Adam Shaw
2018 Full Depth Concrete Patching - Part 2 Complete December, 2018
Annual Surface Seal Street Maintenance Project Complete August, 2018 $18,500
2018 Oil & Chip Street Maintenance Project Complete August, 2018 $224,878
2018 Full Depth Concrete Patching - Part 1 Complete August, 2018 $91,750
2018 Pavement Marking Project In Progress August, 2018 $31,161
Airport Road West Reconstruction Project In Progress May, 2018 $2,223,395
MCORE Project 1 - Green St from Wright St to Busey Ave In Progress April, 2019 $8,878,600
Windsor Road Pavement Reconstruction Project Postponed $4,064,796